Decking a floor

What goes into a suspended deck, per square metre — and what has to be right before it is cast

Decking is the day the design becomes a building. It is also the one item most often estimated from a half-remembered figure, which is a pity, because the quantities are simple arithmetic and the thing that actually costs money is not the concrete.

This page gives quantities, not prices. Nigerian rates move month to month, and a page quoting them would be wrong before it was read — which is why Structura holds prices on your device, in naira you set yourself, and publishes none.

Per square metre of deck

For the common case: a 150 mm slab with 225 × 450 beams on roughly a 4 m grid, grade 25 concrete at a 1:2:4 nominal mix.

ItemPer m²Where it comes from
Concrete, slab0.15 m³ the thickness itself
Concrete, beam webs0.034 m³ 0.5 m of beam per m² on a 4 m grid, 225 × 300 below the slab
Concrete, total0.18 m³ the number to order against
Cement1.2 bags 6.3 bags per m³ at 1:2:4
Sand0.08 m³0.44 per m³
Granite0.16 m³0.88 per m³
Reinforcement15–20 kg ~85 kg/m³ in the slab, ~120 in the beams
Formwork contact area1.3 m² slab soffit, plus both sides and the soffit of the beams
Props~1 no. about 1 m centres under the slab, closer under beams

Notice that a square metre of deck needs 1.3 square metres of formwork. Formwork is measured by contact area, it is usually a bigger item than the concrete it shapes, and what determines its cost is how many times the plywood and props are reused — a programme question, not a drawing one.

Worked: a 100 m² deck

About the footprint of a three-bedroom flat, at the quantities above:

Concrete 100 x 0.184 = 18.4 m3
Cement 18.4 x 6.3 = 116 bags
Sand 18.4 x 0.44 = 8.1 m3
Granite 18.4 x 0.88 = 16.2 m3
Steel 100 x 17 = 1700 kg (from the schedule, not from here)

Formwork 100 x 1.3 = 130 m2 contact area
Plywood 130 / 2.98 = 44 sheets per use (2440 x 1220)
Props say = 100 no.

The site rule of one bag per square metre is the slab on its own — 0.15 × 6.3 = 0.95. It is a good rule and it quietly leaves out the beams, which is where the missing fifth of the order goes.

Every figure here is net: the quantity in the finished floor, not the quantity to buy. Add an allowance — often around 5% on concrete and 3 to 5% on steel — and say on the bill which of the two the bill is showing, or nobody comparing two estimates can tell whether one is cheaper or just measured differently.

Before the mixer starts

An hour of checking here is worth more than anything that can be done afterwards. In the order they are worth doing:

The pour, and the fortnight after it

What moves the cost without changing the drawing

Two identical decks can differ substantially in price, and the variables are almost never the ones people argue about:

Get the quantities out of the design, not off this page

Structura bills every design it does: concrete by member, formwork, reinforcement by the kilogramme, packed into the 12 m lengths you actually buy. You price it with your own naira rates, set once in Settings and stamped with the date they were set — and the bill states whether it is showing net or gross quantities, because a client comparing two estimates cannot otherwise tell.

Open Structura in your browser

On Android, get it on Google Play; on iPhone and iPad, get it on the App Store — same account as the browser.

Next