Soil bearing capacity in Nigeria

Where the number in your footing calculation comes from

Every foundation calculation starts with one number — the allowable bearing pressure — and it is the number in the whole design least likely to have been measured. It gets inherited from the last job on the same street, or taken as "150" because that is what everybody uses.

This page is about where that number should come from, what Nigerian ground is actually like, and how the value you settle on decides the foundation you end up drawing.

What the number means

Soil fails in two different ways, and the allowable pressure has to keep both away:

Two footings can pass the same bearing check and still crack the building between them: what damages a structure is differential settlement, one column dropping more than its neighbour. That is a reason to keep pressures uniform across a building, not just below a limit.

Presumed values, for preliminary sizing

BS 8004 gives presumed bearing values by soil description. They are explicitly for preliminary work — a starting point to get a size on paper, to be confirmed by test.

SoilPresumed value
kN/m²
Dense sand and gravel> 600
Medium dense sand and gravel200–600
Loose sand and gravel< 200
Compact sand> 300
Medium dense sand100–300
Loose sand< 100
Very stiff or hard clay300–600
Stiff clay150–300
Firm clay75–150
Soft clay and silt< 75
Very soft clay, peat, made ground not to be relied on

The 150 kN/m² used throughout these worked examples sits at the top of "firm clay" and is a reasonable presumed value for the firm lateritic soil much of Nigeria is built on, a metre down. It is not a value to design a block of flats on without a test.

What the ground is like, by region

Broad strokes — every site is its own site, and the point of the list is to know what you are looking for:

Two things override all of it. Made ground and old borrow pits can put a metre of rubbish under one corner of a plot and nothing under the rest. And a high water table cuts the bearing capacity of a granular soil to roughly half what the same soil gives when dry, as well as making the excavation a pumping job.

When a test stops being optional

A site investigation is cheap next to a foundation, and absurdly cheap next to a foundation that has to be repaired. Ordinary practice, and worth insisting on:

SituationWhat is normally enough
Bungalow, familiar lateritic ground Trial pits at the corners; check the founding stratum is what you assumed and is continuous
Duplex or two suspended floors Trial pits plus a CPT sounding or a light borehole
Three storeys and up, or any coastal or filled site Boreholes with SPT to depth, reported by a geotechnical engineer, with a stated allowable pressure and a settlement estimate
Soft clay, peat, deep fill, or a neighbour with cracks Full investigation before the foundation type is chosen, not after

When an SPT report does arrive, the descriptions map onto the presumed-value table like this:

SPT NSandsClays
0–4Very looseVery soft to soft
4–10LooseSoft to firm
10–30Medium denseFirm to stiff
30–50DenseVery stiff
> 50Very denseHard

Correlations from N to an allowable pressure exist, and they belong to the geotechnical engineer who saw the borehole log, the water table and the soil descriptions. Reading a bearing pressure off an N value at a desk is how a footing gets designed on a number nobody is accountable for.

What the number does to the foundation

The same column — 410 kN in service, from the worked takedown — on a 4 m × 4 m grid, founded on different ground:

Allowable
kN/m²
Pad needed Share of
the bay
Sensible answer
2001.6 m sq16% Pads, comfortably
1501.8 m sq20% Pads — the worked example
1002.2 m sq30% Pads, but check they clear each other
752.5 m sq39% Compare a raft on cost
503.1 m sq59% Raft
< 40—— Raft if settlement allows it, otherwise piles

Sized as A = 1.15N / qallow, the 15% covering the footing's own weight and the backfill over it — the same start as the pad footing example.

The useful rule is in the third column. Once the pads are taking much more than about half the footprint, the ground between them is doing nothing, the excavation and formwork of many separate pits costs more than one slab, and a raft is both cheaper and stiffer — stiffer being the part that matters, because a raft spreads differential settlement instead of letting each column find its own level.

Below that, it is piles, and piles need a soil model that only comes out of a proper investigation — end bearing, shaft friction, the depth of the competent stratum. That is where Structura stops: it designs pads, strips and rafts, and when a raft will not do it says so rather than producing something plausible.

Try the sizes on your own building

Enter your allowable bearing pressure and Structura designs the footing to BS 8110 — sizing on the service load, then bending, vertical shear and punching shear at ultimate, with the bar schedule and quantities. Pads, strips and rafts are all in, and single members are free to run, as many as you like.

What it will not do is calculate settlement, and every foundation sheet says so plainly. A PASS means the pressure and the concrete check out — not that the building will not move.

Open Structura in your browser

On Android, get it on Google Play; on iPhone and iPad, get it on the App Store — same account as the browser.

Next